How to build a submittal register

A submittal register is the list of every document, sample and closeout item the contract requires from your subs and suppliers, with who owes it, who reviews it and when it is due. Built well, it is the earliest warning you have that a long-lead item is going to arrive late. This guide shows how to build one from the specifications and back-schedule each submit-by date from the dates in your schedule.

1. Start with Division 01

Before you read a single technical section, read the general requirements. In a MasterFormat specification the submittal procedures usually sit in section 01 33 00 (Submittal Procedures), and closeout items in 01 77 00 or 01 78 00 (Closeout Procedures and Closeout Submittals). Look for:

2. Go section by section

Each technical section has a “Submittals” article in Part 1 (General), often article 1.3 or 1.4, sometimes split into Action Submittals, Informational Submittals and Closeout Submittals. Work through the table of contents in order and add a row for every distinct item, not one row per section. Section 08 71 00 (Door Hardware), for example, typically asks for product data, a hardware schedule, keying schedule, samples on request, maintenance data and a warranty: that's five or six rows with different reviewers and due dates.

Also check the drawings. Delegated-design items (pre-engineered stairs, cold-formed framing, fire sprinkler layouts) are often called out on the structural or mechanical sheets with their own submittal requirements, including an engineer's seal from the sub's designer.

Tip

Don't wait for the perfect register. Get the long-lead items in first (structural steel, elevators, switchgear, curtain wall, rooftop units, doors and hardware), then fill in the rest over the first two weeks.

3. Action, informational and closeout submittals

The type decides what the reviewer has to do and how you should chase it.

In SubmittalKit the type is a column (product data, shop drawings, samples, O&M manual, warranty, certificate or other), which later lets you filter the closeout package to just the O&M manuals, warranties and certificates.

4. Assign the sub and the reviewer

Every row needs one responsible company: the sub or supplier who prepares the submittal. If a supplier deals with you directly, list the supplier. Every row also needs a reviewer: the architect, or the structural, mechanical or electrical engineer named in the consultant list, or your own office for record-only items. When you know who reviews what, you can tell an architect “you have four items past their review time” instead of “we're waiting on you”.

5. Number every item

A good number is readable without the register in front of you. The common pattern is spec section, sequence and revision: 05 12 00-001.0 is the first structural steel submittal, original submission; 05 12 00-001.1 is its first resubmittal. Never renumber an item when it's resubmitted. The revision suffix is what keeps the history straight. SubmittalKit allocates the sequence for you and lets you change the format per project.

6. Back-schedule the submit-by date

This is the step most spreadsheets skip. Instead of guessing a submit date, start from when the material must be on site and work backwards:

Submit by = required on site − lead time − review time − buffer, all counted in working days on the project calendar.

Worked example: hollow metal frames (08 11 13), shop drawings

  • Required on site: Monday, April 5, 2027 (framing starts that week)
  • Lead time: 20 working days · Review time: 10 · Buffer: 5 · Total: 35 working days
  • Project holidays in that window: Monday, February 15 and Friday, March 26 (Good Friday)

Counting back 35 working days from April 5, skipping weekends and both holidays, lands on Thursday, February 11, 2027. A calendar-day count (35 days before April 5) would say March 1, almost three weeks too late. That gap is exactly where frames end up arriving after the framers.

Recalculate whenever an input changes. If the schedule slips a week, the submit-by date moves with it. If the supplier's lead time doubles, you see the new date the same day. SubmittalKit does this automatically from your project calendar (Monday to Friday by default, plus the holidays you list), and our free submittal log template does the same in Excel with the WORKDAY function.

7. Keep it alive every week

A register only helps if someone reads it. Once a week:

  1. Filter to items not yet submitted with a submit-by date in the past or in the next 14 days, and call each sub.
  2. Check items in review: date submitted plus review time tells you which reviewer to chase.
  3. Read every “revise and resubmit” and “rejected” item with its comments, and agree a resubmit date with the sub.
  4. Update status and ball in court so anyone on the team can answer “where is it?”.

Common mistakes