RFI log template

A clean request-for-information log with ball-in-court, due dates and cost and schedule impact columns. Free to download for Excel, Google Sheets or LibreOffice.

Download the template

Excel version: “RFI log” sheet with a frozen, filterable header, wrapped text, dropdowns for status and the impact flags, plus a “How to use” sheet. CSV version: the same columns and example rows. Three example RFIs are marked in the Notes column; delete them before you start.

What each column is for

ColumnWhat to enter
RFI #Sequential per project: 1, 2, 3… Never reuse a number, even when an RFI is withdrawn.
SubjectA short, searchable title: location plus topic, e.g. “Footing step at grid C/4”.
QuestionOne question, with the sheet, detail, grid line and spec article it refers to.
Suggested answerYour proposed solution. It is usually faster for the designer to agree than to start from nothing.
Date sentWhen the RFI went out.
FromWho asked: your project engineer, the superintendent, or a sub through you.
Ball in courtWho owes the next action right now: the architect, an engineer, the owner, or you.
DueWhen you need the answer to avoid a delay. If that is sooner than the contract response time, say why in the question.
AnswerThe designer's response, word for word.
Date answeredWhen the answer came back. Days open = date answered minus date sent.
Cost impact (Y/N)Will the answer change the contract sum? Flag it when you send, and update it when you get the answer.
Schedule impact (Y/N)Will it change the schedule? Same rule: flag early, confirm later.
StatusDraft, open, answered or closed (dropdown).
NotesFollow-ups, related submittals, or the ASI or change document that resolved it.

An example row

RFI 1: Footing step at grid C/4

Question: S-201 detail 3 shows a 2'-0" footing step at grid C/4, but geotechnical report section 6.2 recommends one bearing elevation along the whole east wall. Is the step still required? If yes, confirm its location and the bottom-of-footing elevation on each side.

Suggested answer: Delete the step and carry the footing at the geotech bearing elevation along grid C from 3 to 5.

Ball in court: structural engineer · Due: 4 working days after sending · Schedule impact: yes (footing forms are booked)

Notice what makes it answerable: one question, the exact detail and report section, a proposed answer the engineer can accept with one word, and a due date tied to real work. Our guide on how to write an RFI that gets answered goes through this in more detail, with a bad example rewritten.

Keeping the log useful

Run it online free

SubmittalKit numbers RFIs per project, stores attachments, lets the architect answer through a private link without an account, flags RFIs past due on the dashboard and prints any RFI as a PDF.